City Begins 2015 Street Resurfacing Program

PITTSBURGH, PA (April 6, 2015) - The Department of Public Works will begin the 2015 Street Resurfacing Program the week of April 6, 2015. The following streets will be milled and paved, weather permitting:

Penn Avenue (Centre to S.Euclid) - Milled: April 6; Paved: April 7, 10

N. Euclid Street (Station to Stanton) - Milled: April 7; Paved: April 8

Baum Square (S. Euclid to S. Highland) - Milled: April 6; Paved: April 9

S. Highland Avenue (Centre to Penn) - Milled: April 6; Paved: April 9

Eva Street (S. Euclid to S. Beatty) - Milled: April 7; Paved: April 9

S. Whitfield (Baum Blvd to Penn) - Milled: April 7; Paved: April 9

S. 18th Street (Wharton to Mary) - Milled: April 8; Paved: TBD

S. 18th Street (Mission St Bridge to St. Patrick) - Milled: April 8; Paved: TBD

S. 21st Street (E. Carson to Josephine) - Milled: April 9; Paved: TBD

The work will be performed in the evening/overnight between 6:00 p.m. and 6:00 a.m.

###

 

 