PITTSBURGH, PA (August 19, 2020) This week, the City of Pittsburgh’s Department of Mobility and Infrastructure (DOMI) has completed the landslide remediation of a section of Forward Avenue / Commercial Street below the intersection of Summerset Drive in Squirrel Hill.
A subsidence required the removal of landslide material, construction of a steel beam retaining wall and reconstruction of the roadway. This project was started on February 10, 2020 and completed on August 18, 2020 at a cost of $631,800.00. The contractor was Allison Park Contractors.
All barriers have been removed and full vehicle access is permitted.
Comments and questions can be directed to 412-255-8850. Details of the project can be found here.