PITTSBURGH, PA (September 23, 2020) The City of Pittsburgh’s Department of Mobility and Infrastructure (DOMI) is pleased to announce the opening of Buente Street.
Buente Street was closed on August 24, 2020 to replace a wooden retaining wall with a modular block wall thereby stabilizing Buente Street. The opening of Buente Street allows traffic to once again use this street in the Spring Hill - City View neighborhood. This road closure is part of the List Street Landslide Remediation project. The entire project is anticipated to be completed this fall.