PITTSBURGH, PA (November 3, 2020) The City of Pittsburgh’s Department of Mobility and Infrastructure is announcing an inbound lane closure of Itin Street between Concord Street and High Street in the Spring Hill neighborhood of the City starting Tuesday, November 3, 2020. We will be erecting a 32’ x 32’ crane mat and positioning a crane in the right of way for the construction of precast steps on Itin Street leading up to Vista Street. The work is being performed by A. Merante Contracting.
Traffic on Itin Street will be one lane, alternating traffic with certified flaggers around the clock for 3 days.
We appreciate your patience and cooperation during this time.
If you have any questions regarding this project, please contact Robert Michalko, Project Manager at robert.michalko@pittsburghpa.gov.